DONE: All planned items, albeit with delay. Gui sent the initial spec sheet to Dragino on 2016-07-29. Pau had great success on his tour around Germany. Gio reviewed several pull requests and commits. Nico attended different events in Latin America, meeting members of LACNIC among others.
Define a task shortlist for week 04/aug – 11/aug
Website https://librerouter.org hasn’t progressed as expected (Maureen was unavailable). Consider Scann (from AlterMundi) taking charge. Assigned-to: Scann, Nico